How to write a construction daily report

What to record on site every day, and how to write it so it still holds up months later in a claim or dispute.

By Amir Pakshir · Updated Nov 2026

A construction daily report is the written record of one day on a job site: who was there, what was built, what got in the way and what changed. On a dispute, a delay claim or a change order, the daily report is often the only evidence written on the day it happened, so it has to be complete, factual and dated.

What to include

SectionWhat to write
HeaderProject name and number, date, report number, author, superintendent or PM.
WeatherConditions and temperature in the morning and afternoon, and any hours lost to weather.
ManpowerEach trade or subcontractor, head count and hours.
EquipmentEquipment on site, hours used and idle.
Work completedWhat was done, where (grid, floor, room) and how much, in measurable terms.
DeliveriesMaterials received, supplier, quantity, and anything damaged or short.
Inspections and visitorsInspector, owner, architect or engineer visits, and the result.
Delays and issuesWhat stopped work, the cause, who was affected and for how long.
Changes and instructionsVerbal directions from the owner or design team, RFIs raised, extra work performed.
SafetyToolbox talks, incidents, near misses, corrective actions.
PhotosDated photos of progress, issues and anything that will be covered up.

Write it so it holds up later

Example entry

Work completed: Level 2 framing, grid C to F, 85% complete. Hung 40 sheets of drywall in units 201 to 204.
Delays: Concrete pump arrived 2 h late (supplier); 6 laborers idle 7:00 to 9:00. Notified the owner's rep at 9:15.
Instructions: Architect asked on site to move the kitchen outlet in unit 203 by 18 in. RFI #14 sent at 2:30 pm.
Photos: 12 attached (progress, pump arrival time, outlet location).

Watch the 1-minute video

Construction Daily Report App for iPhone | ParsReport AI
Subscribe on YouTube for more →

Write the daily report in two minutesParsReport covers crew, subs, materials, equipment, delays, safety and photos, with on-device AI to write it up, and sends a clean PDF with your marked-up plan sheets before you leave the site.

See ParsReport →

More guides